1. Proj. NameCivil, Steel Structure Construction Works for Control Room & MCC

of EOD Project

2. ClientOriental Union Chemical Corporation (OUCC)

3. Proj. PeriodDec. 2010~Dec. 2011

4. Proj. Description

The project is to construct a 3 stories steel structure control room & MCC building located at the south of EA#2 unit of EOD Project for Oriental Union Chemical Corporation (OUCC), with the building area of 44.1M × 13.6M and height 16.7 M. Work content, PC pile hole cleaning, civil foundation, steel structure fabrication and hoisting, deck plate, wall interior with galvanized color steel wave composite panels, high-tech/ high fireproof performance of aluminum-magnesium alloy double complex board at exterior wall, calcium silicate board ceiling, and light steel partition walls.

5. Major construction item:

  66 piece PC pile hole cleaning, reinforced rebar cage fabrication, expansion R.C. pouring.

  Building footprint excavation, backfilled, tampering, and embedded anchor bolts.

  450T steel structure fabrication, 1,170 M2 deck plate, field welding, hosting, and 926M2

interior wall galvanized color steel wave composite plate.

  1,365M2 galvanized aluminum-magnesium alloy double complex board at exterior wall.

  688M2 light steel partition walls, 868M2 calcium silicate board located inside of exterior

wall.

  746 M2 insulated waterproofing roof.

Communication, Power Cable and Conduit, Site Switching Station.