1.
Proj. Name:Establishment
of No.2 Test Run Platform
2.
Client:Civil
Aeronautics Administration / CKS Air Port Station
3.
Proj. Period:July.
2006∼Nov. 2007
4. Proj. Description:
The established purpose of test-run platform is aiming to level
down turbulence flow while airplane engine is at early starting. A
noise dissipating wall consisting of sound absorption panel and
steel structure is erected right behind the test run platform for
noise reduction.
5. Major construction item:
◆
Civil work for test-run platform
◆
Steel structure with expanded metal for noise reduction and
airflow refraction
◆
Civil work for noise dissipating wall
◆
Steel structure for noise dissipating wall
◆
Sound absorption panel
◆
Vehicle control gate
|