1.
Proj. Name:SCR
De-NOx Turn-Key Project for 90MT Boiler
2.
Client:Linyuan
Advanced Materials Technology Co., Ltd. (a member of CSRC/TCC Group)
3.
Proj. Period:Oct.
2018∼July
2019
4. Proj. Description:
This Project is in turnkey basis to reduce existing 90MT Boiler NOx
emission by providing an new SCR De-NOx
System at Linyuan Plant, including basic & detailed design、CFD
of flue gas flow、certificates
gained、whole
system of the SCR De-NOx
Facilities、together
with associated EPC scopes. After the
Project is accomplished, the flue gas emission of NOx
Concentration at SCR exit will be reduced to
≦25
ppmv with NH3-Slip
≦5
ppmv in the inlet flue gas conditions of 143,600 Nm3/hr flow rate
& 100 ppmv NOx
concentration.
5. Major construction item:
◆
SCR De-NOx
Equipment including De-NOx Catalyst Modules.
◆
Shoot Blowers for De-NOx
Catalyst Modules (incl. Spray Nozzles).
◆
AIG (Ammonia Injection Grid) with NH3 Spray Nozzles.
◆
20% NH3 water solution feeding pump x 2 sets (incl. frequency
converter motors).
◆
Ammonia dilution Blower x 2 sets(incl.
frequence conventer motors).
◆
Ammonia water solution vaporizer with electrical heater and atomization
nozzles.
◆
New SCR Reactor and Exp. Joint added with existing Flue Gas Duct
modification.
◆
Painting and refractory/insulation.
◆
CEMS for online analyzers (NOx/NH3/O2)、Gas
detectors、and
I&C revamping works.
◆
With associated works including civil foundation、steel
structure、stairs
& ladders、
Pipings、ancillary
equipment
、electrical power(incl.
new MCC)、instrument…,
etc.
|