1.
Proj. Name:CPCT
3/4 E.F. H2S
Waste Sour Gas Emission Improvement Project
2.
Client:CPC
Tao-yuan Refinery
3.
Proj. Period:April
2021∼Aug.
2022
4. Proj. Description:
This Project is for CPCT to reduce the H2S
waste sour gas in the 3/4 Elevate Flare Pipelines in accordance with the
Self-Improvement requirements of air pollution prevention and control.
Therefore, it is planned to add a Unit of waste sour gas Scrubbing
Facilities within the limited area of 8Mx17M. By using new added Scrubbing
Facilities, it is expected that the concentration of H2S
emission can be effectively reduced at least
≧95%
in case of the Max. 3,000 Nm3/h waste sour gas flow rate with
41.2Vol% H2S
inlet content. Meanwhile, the other requirements of system pressure drop≦1,200mmH2O,
Dust removal≧50%,
COD of effluent≦1,000
mg/L are also needed to be met.
5. Major construction item:
◆
H2S
waste sour gas Scrubbing Facilities x 1 Unit (Incl. Duplex 2205/316L Inlet
Barrels,
316L
Disengagement Horizontal Vessel, Teflon Reverse jet Nozzles (x4),
Froth Columns,
PPGC Chevron Demisters, Duplex 2205 Static Mixer……etc.).
◆
Scrubbing Circulation Pump x 2 sets, Liquid Caustic Pump x 2 sets, Liquid
NaOCl
Pump x 2 sets.
◆
FRP
Liquid NaOH Tank x 1 set and NaOCl Tank x 1 set.
◆
16”/12”∮H2S
waste sour gas Inlet/Outlet Pipelines retrofitted and/or new added with
Shutoff Valves (x4).
◆
Process & Utility Piping System w/different kinds of Material, Effluent
Wastewater Piping.
◆
Civil Foundation, Steel Structures, Operation Platforms, Dikes and related
Acquisition of
Government Permits and Construction License Application.
◆
Instruments Incl. Control Valves, Radar/Ultrasonic Liquid L/T, Magnetic or
D/P Flow
meters, Density Transmitters, PH/ORP Analyzers, Thermometer/ Pressure
Gauges, etc.
◆
Power Equipment Incl. MCC Panel, Site Explosion-proof Lighting Fixture,
Grounding,
Communication, Power Cable and Conduit, Site Switching Station.
|