Proj. Name:18''
Smokeless Flare (C0630) System Revamping Project (MEF-15)
Area
10 Waste Gas Flare Environmental Safety Improvement Project
(MEF-16)
2.
Client:China
Petrochemical Development Corp. - Toufen Plant
3.
Proj. Period:Nov.
2010∼Nov.
2011
4. Proj. Description:
To integrate the Engineering, Procurement, Construction & Commissioning work
as a complete turn-key EPC project. Work is starting from dismantle the
existing flare tip and replaced with the new 18’’ & 24’’ smokeless flare tip
by using the common support structure of the existing elevated flare. Except
the renewed of two (2) sets of flare tip and its entire combustion system of
the flare; in addition, to add a new waste gas collecting trunk line from
the new unit to flare. The work is also including the revamp of piping,
insulation, scaffolding and a new Water Seal Drum with civil foundation,
instrumentation & control system together with the commissioning work after
dismantled the existing piping system at the vicinity of the flare riser.
5. Major construction item:
◆
Renewed
of 18” & 24’’ flare tip (Including igniter and the ignition control panel).
◆
Fabricate
a new Water Seal Drum with its civil foundation.
◆
Repair
the existing two (2) seal drums.
◆
Revamp
of piping, insulation and instrumentation.
◆
Integration
and rectification between the interface of new and old equipment / piping /
electrical / instrument and issuing the
required design drawings.
◆
Comply
with Client dominated commissioning and training work.
|