New 72” Flare Tip
Installation Completed |
New K.O. Drum(L) &
Water Seal Drum(R) |
1.
Proj. Name:#4
Elevated Flare Revamping Project
2.
Client:CPC
Ta-lin Refinery
3.
Proj. Period:Mar.
2011∼Dec. 2011
4. Proj. Description:
This project is to renew the ignition panel and
72” Flare Tip on Ta-lin No.4 Elevated Flare Unit, design and fabricate new
Water Seal Drum & K.O. Drum, and install new flare slop oil pumps.
Construction also includes piling, civil foundation, Steel structure,
Platform, Piping, Grounding, Lightings, Power Electric, Controlling
Instruments, insulation, painting……, etc.
5. Major construction item:
◆
New
Added Water Seal Drum (D-6522A 5461 ID x 6331 TT)
◆
New
Added K.O. Drum (D-6520 5200 ID x 22000 TT)
◆
Remove
54” flare tip and Molecular Seal
◆
Install
72” flare tip and replace 54” Molecular Seal with 54”φstraight pipe
◆
Install
pumps (P-6521 C/D Flare Slop Oil Pumps)
◆
Install
72” Butterfly Valve 2 sets and 72” MOV 1 set
|