1. Proj. NameNew construction project (mechanical, electrical & air conditioning)

of Kinmen winery fermentation building

2. ClientKinmen Kaoliang Liquor Inc.(KKL)

3. Proj. PeriodAug. 2017Apr. 2022

4. Proj. Description

The project is set up due to KKL intends to further improve and optimize liquor quality. It’s divided into two parts namely civil / architectural, and mechanical / electrical & air conditioning. The project is in association with civil / architectural schedule to complete the electrical work, fire protection, plumbing, fermentation pond conveyor system, liquor soup collecting system, air compression system and HVAC system, etc.

5. Major construction item:

  Grounding and lightning system.

  HV switchgear, DP switchboxes, lighting and busway system.

  Telecommunication/information/television, CCTV and emergency rescue equipment.

  Plumbing system including tap water, drainage system and raining water recovery

equipment.

  Fire protection system including firefighting equipment, fire alarm, PA, smoke evacuation

system, fire barrier system.

  Conveyor system into fermentation pond including six (6) tipping machines, ninety (90) belt

 conveyors with its electrical equipment, PLC control equipment and system start up, etc.

  Liquor soup collecting system including liquor soup collecting tank, piping and its electrical

equipment, system start up, etc.

  Air compression system.

  HVAC system including four (4) chillers, ten (10) water pumps, four (4) heat pumps, eight

(8) cooling towers, two (2) expansion tanks, twelve (12) heat exchangers, eighteen (18) air

handling units (AHU), twenty two (22) separate type air conditioners, fifty three (53)

ventilators, twenty four (24) air curtains with its control equipment and installation works,

etc.

  Ventilation ductworks including integrate type duct, flexible duct, return air box, ABS made

air grill, air outlet fire damper, check damper, inspection access door, etc.

  HVAC system including water piping system & cold insulation work (23,964m2) of refrigerated

warehouse.

  Temporarily E & M engineering and quality inspection work of all material and equipment.