1. Proj. Name:EOD Plant Instrumenation Installation Project

2. Client:Oriental Union Chemical Corporation (OUCC)

3. Proj. Period:Sep. 2011∼Mar. 2012

4. Proj. Description:

This project is to install control instruments for OUCC EOD plant which includes electrical piping, wring, instrument installation for process area, tank area, filling station area and control room marshaling panel wire connection.

5. Major construction item:

◆   Instrument wiring:42,500M

◆  Instrument conduits:14,560M

◆  TUBE SMLS 316SS,1/2"OD:2,400M

◆  CONTROL VALVE:231sets

◆  Junction Box:35 sets

◆  PRESSURE TRANSMITTERS:68 units

◆  D/P TRANSMITTERS:40 units

◆  TEMPERATURE TRANSMITTERS:10 units

◆  RTD(Pt100) SENSOR:57 units

◆  PRESSURE GAUGE:82 pcs

◆  TEMPERATURE GAUGE:37 pcs

◆  MASS FLOWMETER:21 sets

◆  VIBRATION TYPE LEVEL SWITCH:37 units

◆  PRESSURE SWITCH:9 sets

◆  PITOT TUBE:5 sets

◆  GAS DETECTOR:12sets

◆  GAS BLANKETING REGULATOR:15 sets