1. Proj. NameMAN、OSBL、BDO and H2 static facility relocation project

2. ClientTCC Chemical Corp.

3. Proj. PeriodSep. 2009∼Oct. 2011

4. Proj. Description

Relocating of MAN、OSBL、BDO and H2 static facilities and equipments (Includes: Reactors, Drums, Vessels, Columns, Tanks, Heat Exchangers etc…). The project consist of dismantle, hoisting, transportation and re-constructions. This project also includes installation of 11 new carbon/stainless steel tanks. The work includes the construction of: stairs, platform, fire-hydrant system, foam and mist piping.

5. Major construction item:

item

contents

BDO
(2300)

THF
(2400)

GBL
(2500)

H2

MAN-2

OSBL

1

Equipment relocation

51

12

22

64

37

11(new)

total

186 sets

New Tanks
11 sets

2

Industrial license

40

13

9

29

16

 

total

107 set

 

3

Facility total mass

724T

63T

93T

550T

770T

CS:95T
SS:87T

total

2200T*

New 182T

Note : *The demolition of weight does not include the weight of R-1311, but this project

include the adjustment associated with the removal and  installation work as

performed by the technician dispatched from vendor.