MCC and the electrical room power panels
are arranged and installation completely |
2500KVA, 300KVA Non-crystallized
Transformer and 300KW Diesel Generator |
1.
Proj. Name:CPC
Ta-lin Refinery Area G Electrical Equipments and Power
Distribution
Project
2.
Client:CPC
Ta-lin Refinery
3.
Proj. Period:Aug.
2010∼Mar. 2012
4. Proj. Description:
This project is providing CPC Ta-lin Refinery
Area G (Spherical Tanks Farm Area) for the designed electrical equipments
and power distribution system. Which consisting of electrical material &
equipment supply, installation, construction, inspection, testing and
commissioning for power distribution, lighting, grounding, intercom and
public address.
5. Major construction item:
Main equip. |
Specification |
Quantity |
High Voltage Power Panels & TPC’s MOF
|
12 / 24KV |
3 units |
Low Voltage Power Panels and Capacitor
Panels |
460V |
3 units |
Motor Control Center |
460V |
22 units |
Non-crystallized Transformer |
2500KVA, 300KVA |
2 units |
Lighting Panel |
220V |
8 units |
Diesel Generator and Automatically Switch
Panel |
300KW |
1 unit |
UPS and DC Systems |
20KVA, 30A |
2 units |
Intercom and Public Address System
|
5 Channels w/ Explosion Proof |
Whole Plant |
Explosion Proof LED Streetlamp |
100W |
80 units |
LED Streetlamp, Light pole 8M Height |
100W |
66 units |
Underground PVC Conduit Bank Embedment
(Including 15 R.C. Manholes) |
|
655 meters |
|