1.
Proj. Name:Tanker
Top Filling Station Expansion for Ta-Lin Refinery No.8 Sulfur
Recovery
Unit
2.
Client:Project
& Construction Div. of CPC Corp. Taiwan
3.
Proj. Period:Nov.
2017∼Mar 2019
4. Proj. Description:
This project is to build two (2) sets of molten sulfur tanker top filling
platform. The pump will transfer the molten sulfur from the existing sulfur
storage tanks (DS-601/602/603) via insulated jacket pipe to the filling
platform.
The melted sulfur is filled from the top of the sulfur tanker through the
loading arm for domestic sales. Work scope is according to
Client’s
design requirement to develop the construction plan, quality assurance plan
and occupational safety and health management plan. The implementation of
the project including detailed design, procurement, construction,
installation and
testing of each
mechanical, electrical and instrument
equipment. And obtain the necessary documents and licensing permits, final
satisfaction acceptance and warranty work.This
Project is achieved
“outstanding engineering award”
of year 2018 given by the Taiwan government.
5. Major construction item:
◆
Renew two (2) sets of steam jacket
sulfur transfer pump (P-601A / B)
◆
Add two (2) sets of molten
sulfur loading arms
◆
Add two (2) sets of pneumatic
stretch stairs
◆
Main molten sulfur conveying
pipe heated by steam tracing and its associated
piping such
as LS, LC, LA and
utility station.
Design spec. of molten sulfur conveying main pipe is K.C.S.
Sch.160 with
heated jacket
◆
Civil foundation with piling
and two (2) sets of filling station including steel structure w/rain
shelter, pipe rack and steel structures fireproofing
◆
Control valves and MCC panels
◆
Explosion-proof PDP, fan,
receptacle and lighting fixture
◆
Grounding system, PA and fire
fighting
|