1.
Proj. Name:Membrane
Stage Vapor Recovery Unit Project
2.
Client:Shimen
Fuel Depot,
Marketing Business Div. of CPC Corp., Taiwan
3.
Proj. Period:Sep.
2019∼Apr.
2021
4. Proj. Description:
This project
is
to build a new Membrane Stage Vapor Recovery Unit to improve vapor recovery
efficiency at the Shimen
Fuel Depot.
This Membrane Stage Vapor Recovery Unit (include activated carbon /
molecular sieve PSA equipment) will make the Shimen Fuel
Depot
comply with the local environmental protection regulations and emission
standards.
The
Vapor recovery
Unit Capacity will be higher than
900Nm3/hr, which should reduce the
HC
vapor emissions by at least 95%,
and the concentration of
fuel
vapor emissions after the treatment of pressure swing adsorption equipment
should be lower
than 300ppm (excluding methane).
5. Major construction item:
◆
Liquid Ring Compressor x 3 sets (Incl. Variable Speed Drive System), Vacuum
Pump
x 3 sets,
Membrane Stage x 9 sets.
◆
Scrubber (Incl. Demister) x 1 set.
◆
Pressure Swing Adsorption (PSA) Unit (Incl. Activated Carbon, Molecular
Sieve) x 2 sets.
◆
Renovate Existing Oil Tank to be Vapor Holder (Incl. Rubber Bubble) x 1 set.
◆
Container Control Room x 1 set.
◆
Vapor, Scrubbing Fluid and various Inlet / Outlet Tie-in Pipelines (OSBL)
◆
Process & Utility Piping System with different kinds of Material, (Oily)
Effluent Wastewater
Piping (ISBL).
◆
Civil Foundation, Operation Platform, Dike and Acquisition of Government
Permits.
◆
Instruments incl. PLC Panel, Control Valves, Magnetic Flip Liquid L/T,
Vortex Flowmeter,
RTD thermometer,
D/P Transmitter, Thermometer/ Pressure Gauge, etc.
◆
Power Equipment incl. Electrical Panel, Site Explosion-proof Lighting
Fixture, Grounding,
Communication,
Power Cable and Conduit, Site Switching Station.
|