1. Proj. NameCPCT Gasoline Vapor Recovery Unit EPC Turn-Key Project

2. ClientCPC Tao-yuan Refinery

3. Proj. PeriodSep. 2023Aug. 2025

4. Proj. Description

This project is to build a new Membrane Stage Vapor Recovery Unit to improve vapor recovery efficiency at the No.1 Loading Unit of Tao-yuan Refinery. This Membrane Stage Vapor Recovery Unit (include activated carbon / molecular sieve PSA equipment) will make the Tao-yuan Refinery to comply with the local environmental protection regulations and emission standards.  The Vapor Recovery Unit Capacity will be higher than 1,200Nm3/hr, which should reduce the HC vapor emissions at least 95%(by Mass), and the concentration of fuel vapor emissions after the treatment of pressure swing adsorption equipment should be 300 vppm (excluding methane).

5. Major construction item:

  Liquid Ring Compressor x 2 sets (Incl. Variable Speed Drive System), Vacuum Pump

x 3 sets, Membrane Stage x 12 sets, Absorbent Feed Pump x2 sets, Absorbent Return

Pump x2 sets.

  Scrubber (Incl. Demister and Stainless steel Raschig Ring) x 1 set.

  Pressure Swing Adsorption (PSA) Unit (Incl. Activated Carbon, Molecular Sieve) x 2 sets.

  50m3 Vapor Buffer Tank (Incl. Rubber Bladder) x 1 set.

  Container Type of Control Room x 1 set.

  Online Analyzer (THC / CH4 ) x1 set

  Vapor, Scrubbing Fluid and various Inlet / Outlet Tie-in Pipelines (OSBL)

  Process & Utility Piping System with different kinds of Material (ISBL)

  Civil Foundation, Operation Platform, Dike and Acquisition of Government Permits.

  Safety Facilities incl. HC Gas Detectors, Flame Arresters, Pressure Relief Valves,

 Breathing Valve, Gas outlet Silencer, etc.

  Instruments incl. PLC Panel, Control Valves, Magnetic Flip Liquid L/T, Vortex Flowmeter,

 RTD thermometer, D/P Transmitter, Thermometer/ Pressure Gauge, etc.

  Power Equipment incl. Electrical Panel, Site Explosion-proof Lighting Fixture, Grounding,

 Communication, Power Cable and Conduit, Site Switching Station.