The existing filling station and tanker trucks
in the No.1 Loading Unit
|
Current site situation of the planned location
for the Membrane Stage Vapor Recovery Unit |
1.
Proj. Name:CPCT
Gasoline Vapor Recovery Unit EPC Turn-Key Project
2.
Client:CPC
Tao-yuan Refinery
3.
Proj. Period:Sep.
2023∼Aug.
2025
4. Proj. Description:
This project
is
to build a new Membrane Stage Vapor Recovery Unit to improve vapor recovery
efficiency at the No.1 Loading Unit of
Tao-yuan Refinery.
This Membrane Stage Vapor Recovery Unit (include activated carbon /
molecular sieve PSA equipment) will make the
Tao-yuan Refinery to
comply with the local environmental protection regulations and emission
standards.
The
Vapor
Recovery
Unit Capacity will be higher than 1,200Nm3/hr,
which should reduce the
HC
vapor emissions
at least 95%(by
Mass),
and the concentration of
fuel
vapor emissions after the treatment of pressure swing adsorption equipment
should be
≦300
vppm (excluding methane).
5. Major construction item:
◆
Liquid Ring Compressor x 2 sets (Incl. Variable Speed Drive System), Vacuum
Pump
x 3 sets, Membrane Stage x 12 sets, Absorbent Feed Pump x2 sets, Absorbent
Return
Pump x2 sets.
◆
Scrubber
(Incl. Demister and
Stainless steel Raschig Ring) x 1 set.
◆
Pressure Swing Adsorption (PSA) Unit (Incl. Activated Carbon, Molecular
Sieve) x
2 sets.
◆
50m3 Vapor Buffer Tank (Incl. Rubber Bladder) x 1 set.
◆
Container Type of Control Room x 1 set.
◆
Online Analyzer (THC / CH4
) x1 set
◆
Vapor, Scrubbing Fluid and various Inlet / Outlet Tie-in Pipelines (OSBL)
◆
Process & Utility Piping System with different kinds of Material (ISBL)
◆
Civil Foundation, Operation Platform, Dike and Acquisition of Government
Permits.
◆
Safety Facilities incl. HC
Gas
Detectors, Flame Arresters, Pressure Relief Valves,
Breathing
Valve,
Gas
outlet Silencer, etc.
◆
Instruments incl. PLC Panel, Control Valves, Magnetic Flip Liquid L/T,
Vortex Flowmeter,
RTD
thermometer, D/P Transmitter, Thermometer/ Pressure Gauge, etc.
◆
Power Equipment incl. Electrical Panel, Site Explosion-proof Lighting
Fixture, Grounding,
Communication,
Power Cable and Conduit, Site Switching Station.
|